Preparing for a
better future
The latest phase of an ambitious expansion plan at the University of
York is up and running smoothly thanks to a cost-effective networking
solution from IT provider XMA, delivered according to the University’s
exact requirements.
An ambitious ongoing expansion plan at the University of York has seen
the organisation face some important IT decisions. With the £750 million
pound project to build a new campus, called Heslington East, expected to
last for at least a decade, staff have been keen to implement effective IT
strategies along the way.
According to Peter Turnbull, the University’s IT services network
manager, in-house staff successfully completed phase one to build
residential college, Goodricke College, but decided they needed extra
help for a second phase. Mr Turnbull said: “The University installed
network connections in study bedrooms and in the main buildings for
office and support staff. We also introduced Voice over IP telephony for the
telephone systems and state-of-the-art building management systems such
as access controlled door locks, CCTV cameras, environmental monitoring
and energy management.”
“As a result of doing that - which was in 600 study bedrooms and associated
offices for support staff - we realized the next phase, which was even larger,
would be more than we could manage while still doing the day job.”
“In the next phase, there were about 7,000 network outlets, spread over four
buildings, and we worked out it would take about a month of a member of
staff’s time working on that – and on nothing else. Instead we decided to find
a partner who could configure all the switches for us, deliver them to the site
and install them. We chose XMA because we viewed them as offering the
best opportunity for creating a partnership rather than just selling us
some boxes.”

Building a resilient network
During the project, which spanned July to early October, XMA supplied
and installed 150 switches along with 15 routing switches. The switches
were at the heart of a resilient network, centred on an OSPF mesh.
Mr Turnbull said: “All of the buildings were interconnected in a spider’s web
arrangement so if any one device failed the others would carry on running.
Obviously that means we can have absolute confidence in our IT services,
which cover office PCs, network access in study bedrooms, CCTV, and controlled
door locks - any conceivable service the network powers basically. As we have
a dedicated PABX for VoIP, we’ve also run some dedicated phone lines to each
building, so if there is a fire or a power loss then a call can still be made to security
or emergency services.”
Cost and time
According to Mr Turnbull, cost and time were key considerations for the
University. He said: “We bore in mind the cost of us of doing the job when we were
evaluating tenders. We knew XMA were already set up with a number of engineers
based in Nottingham, where they could configure the switches before bringing
them to us, ready to go”.
“It was a huge benefit because the number of switches involved would have filled a
large room. However, XMA obtained all the equipment ahead of time and stored it
in their secure storage. They were able to unpack it all, set it up with our bespoke
configurations, test it and bring it to the site piecemeal as was required. Even if
we had had the staff available to do it ourselves it would have cost us more in staff
time than we ended up paying.”
He adds: “A major time constraint was that everything had to be working for the
start of term, part-way through October, and that was delivered. We had always
felt confident XMA would meet our tight timescales as they had demonstrated it
through other projects. There are now a number of academic departments, some
with very high-tech networking requirements, relying on XMA’s work. With the
company’s help, they were all up and running on time.”
A flexible partner
The XMA account manager provided a single point of contact, which also
worked well before and during the project. Mr Turnbull says: “XMA appointed
a project manager to work in partnership with us which was very helpful.
They came to see us on several occasions before we got started and remained
in constant touch.”
As the project progressed, Mr Turnbull says the flexibility shown by XMA staff
was a great advantage, particularly as the network had to be in place before
the buildings could be handed over by contractors. That was because CCTV
and door locks, which relied on the network, had to be working before the
University could take charge of the campus. And, the door locks were also
linked to fire alarms which had to be signed off by fire officers before the
building was deemed fit for use.
Mr Turnbull says: “XMA had a pretty tight timescale to bring staff along to set up
our network the day we could get access to do it. They turned out to be remarkably
flexible. As with any building project there were delays and changes. The IT project
had to be carefully fitted around key site access dates as the campus was a
building site with heavy machinery moving around. They were a number of changes
to the schedule but XMA staff got everything done at short notice. All in all, they
were very cooperative, flexible and responsive.”